Coding Period - Tenth Week Report (Jul 31 - Aug 6)
Overview
During this week I have worked on implementing more functionalities for
the insert
endpoint and also worked on bug fixes.
Accomplishments
During this week, I have worked on:
- Continued working on the implementation to support to multiple data types for Observations
- Continued working on the nested data insertion
- Fixed some bugs
Blockers
After a discussion with the mentors, for now the support for multiple data types is not a priority, so I will continue working on the nested data insertion. I have got far with the implementation, I still need to test it and fix some bugs.
Next Steps
Looking ahead to the next week, my plan is to:
- Continue testing the nested data insertion
- Start working on the update endpoint
Conclusion
I am satisfied with the progress I have made this week. I have got far with the implementation of the nested data insertion, I still need to test it and fix some bugs. I will continue working on it during the next week.